Committee working material

A Working Guide to the Data Center Advisory Committee’s Charge

Neutral committee guide | Draft 1 | September 18, 2026

The committee’s job

Treat the assignment like a public fact-finding inquiry. The committee does not need to decide whether data centers are good or bad in the abstract. It must tell the Board: what Imperial County can support, where it can fit, what rules are missing, what evidence applicants must provide, and how new rules should be applied lawfully.

Practical sequence

Step 1 - Establish the baseline

Charge: Evaluate current General Plan, zoning, ordinances and specific plans.

Read: Land Use Element; Title 9 M-1/M-2/M-3, design, noise and enforcement divisions; relevant specific plans; IID tariff.

Answer: - Where is an enclosed data center permitted now? - Which accessory features trigger a CUP? - Which existing standards control noise, water, generators, setbacks and enforcement? - Which current provisions are clear, ambiguous or missing?

Work product: adopted baseline matrix. Do not debate new policy until members agree on what today’s rules say.

Step 2 - Define the use and its scale

Charge: Identify gaps and needed land-use tools.

Read: rules-and-gaps audit; IID Large Load Tariff.

Answer: - What counts as a data center, yard, campus and accessory generation? - Should adjacent phases and affiliates be aggregated? - Which load tiers require administrative review, CUP, specific plan or development agreement?

Work product: definitions plus an agreed tier table. Use IID’s 20 MW tariff line as the large-load planning unit, not as proof that any site has 20 MW available.

Step 3 - Set objective pass/fail gates

Charge: Determine what regulations are needed.

Read: 20 MW framework; IID study/tariff materials; County water, fire, noise and air rules.

Answer: - What constitutes firm deliverable power? - What water budget and cooling evidence must be independently verified? - What generator, BESS, fire, noise, heat and lighting standards apply? - What proof of financing and project readiness is required?

Work product: model application checklist and required findings.

Step 4 - Define compatibility before drawing a map

Charge: Address proximity to homes, schools, neighborhoods and sensitive uses.

Read: General Plan compatibility policies; Title 9 noise; public-health, air, fire, airport, flood and habitat layers.

Answer: - Which uses require fixed setbacks, performance standards, or both? - Where is 24-hour equipment noise measured, under normal, testing and emergency modes? - When does a generator yard make an otherwise industrial parcel incompatible? - How will cumulative burdens and environmental justice be evaluated?

Work product: compatibility matrix with measurable standards. Avoid a single arbitrary buffer for every impact.

Step 5 - Build the suitability atlas

Charge: Map areas best suited based on land use, infrastructure and energy.

Read: six-area first-pass screen; IID system maps; zoning/parcel maps; water-purveyor, flood, habitat, airport and road layers.

Answer: - Which parcels have the right land-use designation and enough buffer? - Which are near useful grid nodes, subject to IID confirmation? - Which have an identified water and fire-flow solution? - Which fail because of housing, schools, air burden, agriculture, habitat or infrastructure cost?

Work product: red/yellow/green atlas with methodology and caveats. “Near a line” is not “has capacity.”

Step 6 - Choose the planning tools

Charge: Decide whether specific plans or other tools should control location and regulation.

Answer: - Can a countywide ordinance and overlay handle 5-20 MW projects? - At what scale or complexity is a specific plan required? - When is a development agreement justified, and what public benefits/security should it contain? - Should a pre-application fatal-flaw screen occur before full processing?

Work product: tool-selection matrix: by-right, administrative, CUP, overlay, specific plan, development agreement.

Step 7 - Separate new projects from projects in process

Charge: Determine lawful application of new rules.

Read: project entitlement record; any development agreement; tentative/vesting maps; issued permits; California Government Code development-agreement and vesting provisions; County Counsel opinion.

Answer: - What applications or approvals actually exist for each project? - Has any right vested, and for which precise scope? - Can health, safety, nuisance, building, fire or operating requirements still apply? - Which recommendations are prospective only?

Work product: project-by-project legal-status table prepared or approved by County Counsel. Do not use “grandfathered” as a conclusion without identifying the legal instrument.

Step 8 - Write findings before recommendations

For each issue, use four parts: 1. Finding: verified fact with citation. 2. Interpretation: what the fact means and where members disagree. 3. Recommendation: the proposed County action. 4. Implementation: ordinance/plan change, responsible office, timing and enforcement.

Final package: executive summary; baseline law; definitions and tiers; compatibility standards; suitability atlas; project-in-process legal analysis; fiscal/infrastructure findings; ordinance concepts; minority views if unresolved; source library.

Suggested meeting order

  1. Adopt baseline and definitions.
  2. Hear IID, water, fire, air, planning and County Counsel evidence.
  3. Adopt gates and compatibility criteria.
  4. Apply them to the map.
  5. Choose planning tools and transition rules.
  6. Debate findings and recommendations.
  7. Conduct legal and factual quality control.
  8. Submit by January 1, 2027.