Committee working material
Imperial County Data Center Advisory Committee: Section 3 Research Draft
September 18, 2026
This report is delivered as a set of working papers so the committee can use each piece independently:
- 20 MW Scale-and-Siting Framework - load tiers, pass/fail gates, six-area desktop screen, cost and unverified-claim cautions.
- Existing Rules and Regulatory Gap - what the General Plan and Title 9 currently do, including the existing M-1/M-2/M-3 data-center provisions.
- Planning Tools, Compatibility, and Projects in Process - ordinance/overlay/CUP/specific-plan architecture, sensitive-use methods, California transition and vesting framework.
- Draft Findings and Recommendations - Board-package outline with implementation actions and remaining evidence.
- Committee Working Guide - practical sequence for the committee to move through its charge.
- IID Data Request - a draft request for the system facts that cannot be inferred from public maps.
Central conclusion
The County should not choose between a ban and unrestricted data-center development. It should define a lawful path for right-sized projects and require larger proposals to prove power, water, compatibility and financial readiness. IID’s 20 MW tariff threshold supplies a practical large-load planning unit, but it does not establish capacity at any site.
Evidence standards
- Facts, applicant claims and policy judgments are labeled separately.
- A line or substation on a map is a screening lead, not a will-serve commitment.
- “Grandfathered” is not used without a documented legal basis and scope.
- Site names in the desktop screen are study areas, not endorsements.
- Unverified local load comparisons and largest-load ranking remain questions for IID.
- County Counsel reviews ordinance language and every project-in-process conclusion.
Imperial County 20 MW Scale-and-Siting Framework
Desktop working paper | September 18, 2026
The policy choice
Imperial County should regulate projects by the load IID can actually evaluate and serve, not by a hypothetical 300-330 MW campus. IID’s current Large Load Tariff applies to a customer requesting at least 20 MW with an 80% minimum load factor. That makes 20 MW a defensible planning unit, but not a promise of available capacity at any site. Every candidate still requires an IID system-impact, facilities, power-supply and interconnection determination.
Proposed scale framework
Anti-evasion rule: aggregate adjacent parcels, affiliates, shared substations and phased buildings under common control. A 100 MW campus is not five unrelated 20 MW projects.
Pass/fail gates for a 20 MW site
- Power: IID identifies a feasible point of interconnection, deliverable MW and MWh, upgrade scope, schedule, curtailment priority and applicant cost. Line proximity alone does not pass.
- Water: independently reconciled potable, process/cooling and fire-flow budgets. Prefer air or closed-loop cooling; identify the actual water purveyor and legally available supply.
- Land compatibility: industrial entitlement or a clear entitlement path; adequate acreage, drainage and road access; separation from homes, schools, hospitals and incompatible agricultural operations.
- Backup generation: disclose MW, fuel, annual test/run hours, emissions, noise and fuel storage. Large engine farms near housing or light-industrial neighbors fail even if emergency-only on paper.
- Developer proof: parcel control, financing evidence, equipment deposits, schedule, and security for IID/county costs before public money or capacity is reserved.
- Verification after opening: revenue-grade interval meter, annual water and generator-hour reporting, noise/air testing, permit audit rights, enforceable load ramp, decommissioning security and automatic expiration for missed milestones.
First-pass six-site screen
These are study areas, not recommended parcels and not findings of available 20 MW service.
Gateway of the Americas, east Calexico port
- Why screen it
- 1,775-acre planned industrial area; IID completed a Gateway Substation expansion in 2026 for industrial/commercial growth
- Land/use and compatibility
- Large industrial setting and border/logistics access; map buffers to Calexico housing, port/security uses and Alamo River
- Water
- Confirm service capacity and industrial allocation; older plan is not proof of present water
- Generation implication
- Industrial setting is better than a residential edge, but engine count/noise/air still need a parcel buffer
- First fatal-flaw question
- Can IID deliver a firm 20 MW block after committed Gateway growth, and can the local water/sewer systems serve it?
Imperial Industrial Park / Imperial Substation area
- Why screen it
- 121 acres marketed as industrial-zoned; historical 92-kV Imperial Substation record
- Land/use and compatibility
- Reuse of a former cotton-processing/industrial site is preferable to greenfield; verify parcel ownership, active tenants, nearest residences and airport constraints
- Water
- Identify current purveyor, fire flow and cooling supply; marketing page gives no capacity proof
- Generation implication
- Existing industrial use may reduce conflict, but on-site generation should be sited at the interior with modeled noise/air
- First fatal-flaw question
- Is there a parcel with both control and a feasible 20 MW IID interconnection without displacing productive industry?
Luckey Ranch / Brawley industrial area
- Why screen it
- Historical 45.24-acre M-1/light-industrial plan; Brawley has a 92-kV substation/line corridor
- Land/use and compatibility
- Industrial designation and acreage are promising; screen distance to Brawley homes, airport, rail and agricultural operations
- Water
- Confirm City of Brawley water/wastewater capacity and drought/fire-flow constraints
- Generation implication
- Avoid the city edge for a full engine yard; BESS plus limited emergency generation may fit better
- First fatal-flaw question
- Which parcel is close enough electrically but far enough from homes, and what headroom exists at Brawley?
Mesquite Lake / Keystone Specific Plan
- Why screen it
- About 5,100 acres planned for light, medium and heavy industry, offering room for buffers
- Land/use and compatibility
- Strong land-use concept and scale; however the plan itself says major infrastructure is limited and needs substations, water/sewer, roads and drainage
- Water
- A reclamation facility was planned at 2.5 MGD initial/15 MGD ultimate, but current existence/capacity is unverified
- Generation implication
- Large buffers make backup generation more manageable, but infrastructure creation could erase the site’s advantage
- First fatal-flaw question
- Has the water/reclamation and electric infrastructure actually been built, and who pays to bring 20 MW to a parcel?
Holtville industrial/substation area
- Why screen it
- Existing Holtville substation and a permitted 100-MW BESS show a meaningful grid node
- Land/use and compatibility
- Vacant/light-industrial land exists, but the BESS record and local reporting identify nearby homes and a high school. Use only parcels with a demonstrable buffer
- Water
- Confirm city water/sewer and fire flow; no desktop capacity proof
- Generation implication
- This is the clearest warning site: a large generator yard near homes/school should fail compatibility even if the grid works
- First fatal-flaw question
- Is there a different parcel on the node with adequate separation, or should Holtville be excluded?
Niland/Calipatria geothermal-generation corridor
- Why screen it
- Existing Niland generation and project records showing a nearby IID 230-kV corridor make this a logical grid-oriented screen
- Land/use and compatibility
- Rural/energy landscape can provide buffers; evaluate Salton Sea, geothermal, habitat, flood, seismic, air-quality and environmental-justice constraints
- Water
- Potable/process supply is likely the hard gate; test reclaimed/non-potable options and avoid open-loop cooling
- Generation implication
- Better physical separation for engines, but cumulative air burden and disadvantaged-community impacts matter
- First fatal-flaw question
- Can IID identify deliverable load at a suitable node, and is there a lawful low-water cooling/fire plan?
Control case: the Aten/Clark corridor
The Aten/Clark proposed-campus corridor is electrically relevant because the applicant’s study identifies IID’s 230-kV S line and 92-kV R line. It is treated here as a control case, not as a presumed-suitable site: an open question for the committee is whether a smaller 20 MW phase on a better-buffered parcel resolves the land-use conflict. Applicant-hosted feasibility material is not an IID will-serve commitment.
Claims awaiting verification
The following circulating claims are unverified and should be treated as open questions, not established facts:
- Largest single load in Imperial Valley: unverified. IID can answer this in anonymized or banded form without naming a customer.
- $600 million: industry benchmarks show traditional facility construction around $9.8-$13.3 million per MW of IT capacity in Phoenix/Silicon Valley, with U.S. liquid-cooled AI facilities averaging 7-10% more. That implies roughly $196-$266 million for a 20 MW IT facility before the AI premium, with scope caveats. Servers, land, utility upgrades and the difference between utility load and IT load can move the total sharply. $600 million may be plausible for a fully equipped AI project, but it is not a safe generic estimate. It is plainly too low as total construction cost for 300 MW.
Proposed committee action
Direct staff and IID to return with a 20 MW suitability atlas: six to ten study areas, parcel-level buffers, existing zoning, distance to 92/161/230-kV facilities, water purveyor and capacity, flood/airport/habitat constraints, and IID’s red/yellow/green feasibility status. Publish the methodology, not customer-confidential system details. The atlas should show where a right-sized project could work and what evidence any applicant must provide before the County spends time on a proposal.
Sources
- IID/APPA large-load tariff: https://www.publicpower.org/periodical/article/imperial-irrigation-district-board-unanimously-approves-large-load-tariff
- IID guardrails: https://www.iid.com/Home/Components/News/News/1399/30
- IID service maps: https://www.iid.com/power/about-iid-power/power-service-maps
- Gateway Substation: https://www.iid.com/Home/Components/News/News/1452/
- Gateway planning area: https://publicworks.imperialcounty.org/wp-content/uploads/2021/04/Boyle-Engineering-Report-February-2007-Gateway.pdf
- Imperial Industrial Park: https://imperialindustrialparks.com/indoor-facilities/
- Imperial Substation: https://ceqanet.lci.ca.gov/2002071076
- Luckey Ranch: https://ceqanet.opr.ca.gov/2002101107
- Brawley 92-kV project: https://ceqanet.lci.ca.gov/1995102131
- Mesquite Lake plan: https://www.icpds.com/assets/planning/ordinances/title-9-div-5b-mesquite-lake-specific-plan.pdf
- Keystone reclamation record: https://ceqanet.lci.ca.gov/2010011090
- Holtville grid/industrial record: https://ceqanet.lci.ca.gov/2023110549
- Niland plant: https://www.energy.ca.gov/powerplant/simple-cycle/niland-gas-turbine-plant
- North-county 230-kV project record: https://imperial.granicus.com/MetaViewer.php?clip_id=375&meta_id=47331&view_id=2
- Cost trends: https://reports.turnerandtownsend.com/data-centre-construction-cost-index-2025/data-centre-cost-trends
- Cost methodology: https://reports.turnerandtownsend.com/data-centre-construction-cost-index-2025/methodology
Section 3 Working Paper 2: Existing Rules and the Regulatory Gap
Imperial County Data Center Advisory Committee | September 18, 2026
Bottom line
Imperial County does not start from a blank page. Title 9 expressly lists a “data center (within enclosed building)” as a permitted use in M-1, lists “data centers” as a permitted use in M-2, and carries M-2 permitted uses into M-3. A “data center yard” requires a conditional use permit in M-1. This is the central gap: the ordinance identifies the use, but does not scale review to electric load, water, backup generation, heat, operating noise, financial readiness or proximity to sensitive uses. A small enclosed facility and a 20 MW or 300 MW campus can begin in the same use category even though their infrastructure and community effects are different in kind.
What the current framework does
General Plan
The 2015 Land Use Element: - directs orderly development with adequate public facilities; - allows zoning limits where facilities are inadequate or development would impair agriculture or cause leapfrog growth; - identifies specific plans as the tool for large industrial parks or areas needing study when conventional zoning is inadequate; - requires specific plans to address land uses and the location/intensity of water, sewer, drainage, energy and other facilities; - asks whether a specific plan pays its public-service costs, creates permanent jobs, reduces environmental and compatibility effects, adds distinct local opportunity and advances an unmet General Plan goal.
Title 9 land-use ordinance
- M-1: enclosed data center is permitted by right, subject to Title 9. A data-center yard and an electrical generation plant require a CUP.
- M-2: data centers are permitted by right. The zone’s purpose says operations should stay within buildings or screened yards and not emit fumes, odor, dust, smoke, gas, significant noise or vibration beyond the site.
- M-3: incorporates M-2 permitted uses.
- Noise: one-hour limits are 50/45 dBA in R-1 by day/night, 55/50 in other residential, 70 in manufacturing/other industrial, and 75 in general industrial. At unlike zoning boundaries, the limit is measured at the shared property line.
- Enforcement: Title 9 has an enforcement division, but the data-center entries themselves contain no reporting, meter-data, water-use, generator-hour or milestone requirements.
The gaps the committee should close
- No definition. The located provisions do not define data center, data-center yard, campus, IT load, utility load, accessory generation, or common-control/aggregated phases.
- No load tiers. Review does not change at 5, 20 or 50 MW even though IID’s new tariff begins at 20 MW and 80% load factor.
- By-right mismatch. A use with regional power and water consequences may be permitted in M-1/M-2 without a project-specific CUP solely because the servers are enclosed.
- No infrastructure finding. Title 9 does not expressly require IID confirmation of deliverable capacity, upgrade cost, schedule, power supply or curtailment before land-use approval.
- No water standard. There is no data-center water budget, cooling-method preference, independent reconciliation, reclaimed-water analysis or enforceable operating cap.
- No sensitive-use rule. General noise limits help, but there is no setback or performance protocol for homes, schools, hospitals, disadvantaged communities, agricultural workers or habitat.
- Generator ambiguity. A yard or power plant can trigger a CUP, but the ordinance does not clearly classify hundreds of emergency generators, distinguish testing from routine operation, or cap cumulative run hours.
- No heat, light or 24-hour operating standards. The ordinance lacks data-center-specific heat-rejection, glare, security lighting and nighttime maintenance rules.
- No anti-segmentation rule. Nothing located aggregates adjacent parcels, affiliates, shared substations or phased buildings.
- No proof-of-readiness or expiration system. There are no data-center-specific requirements for parcel control, financing, equipment deposits, IID security, load-ramp milestones or decommissioning security.
- No operating verification. No revenue-grade interval-load report, annual water report, generator log, noise confirmation or audit right is tied to the use listing.
- No mapped suitability overlay. The rules identify zones, not parcels where power, water, roads, drainage and separation align.
Pending County Counsel review, amend Title 9 so that: - only genuinely small enclosed facilities below a stated threshold remain administrative/by right; - 5 to under 20 MW requires an infrastructure screen and CUP; - 20 MW and above requires the full IID large-load record, independent water review and enhanced CUP findings; - 50 MW and above, or an aggregated campus, requires a specific plan or development agreement and cumulative review; - all phases under common ownership/control, a common entitlement plan or shared substation are aggregated; - approval reserves no electric capacity and becomes effective only when stated IID and water conditions are met; - permit conditions include operating reports, audit rights, milestone expiration and decommissioning security.
Primary sources
- General Plan portal: https://www.icpds.com/planning/land-use-documents/general-plan
- 2015 Land Use Element: https://www.icpds.com/assets/planning/land-use-element/land-use-element-2015.pdf
- Ordinance portal: https://www.icpds.com/planning/land-use-documents/ordinances
- Title 9 zoning areas and M-1/M-2/M-3 provisions: https://www.icpds.com/assets/5-Zoning-Areas-Established-.pdf
- Title 9 site/design standards: https://www.icpds.com/assets/planning/ordinances/title-9-div-3-2014.pdf
- Title 9 noise: https://www.icpds.com/assets/planning/ordinances/title-9-div-7-2015.pdf
- Title 9 enforcement: https://www.icpds.com/assets/planning/ordinances/title-9-div-13-2015.pdf
- Conservation/Open Space Element: https://www.icpds.com/assets/County-of-Imperial-2016-1642792433.pdf
- Circulation/Scenic Highways Element: https://www.icpds.com/assets/planning/circulation-scenic-highway-element-2008.pdf
- IID Large Load Tariff summary: https://www.publicpower.org/periodical/article/imperial-irrigation-district-board-unanimously-approves-large-load-tariff
Verification note: This audit is based on the County’s posted General Plan and Title 9 PDFs posted as of September 18, 2026. County staff and County Counsel should confirm whether later codified amendments, uncodified urgency measures, policy memoranda or project-specific interpretations alter these provisions.
Draft for committee and County Counsel review | September 18, 2026
Recommended regulatory architecture
Use more than one tool. A countywide ordinance should define and regulate the use; a suitability overlay should identify preferred areas; a CUP should test site-specific impacts; and a specific plan or development agreement should be reserved for a campus whose size or infrastructure demands exceed conventional zoning.
The County’s own Land Use Element supports specific plans where conventional zoning is inadequate for a large industrial park or area needing further study. It also requires the plan to address the location and intensity of water, sewer, drainage, energy and other facilities and to demonstrate public benefit.
A fixed setback alone cannot manage low-frequency fan noise, nighttime testing, exhaust, plume behavior or cumulative generator operation. A pure performance standard can also fail if it lets a project place industrial machinery against a home and promise later mitigation. Use both.
Recommended study standards, not final legal numbers
- Residential, schools, hospitals and care facilities: require discretionary review whenever a data-center building, substation, cooling plant, BESS or generator yard lies within a defined study radius. Establish final distances only after acoustic/air/fire analysis. As a starting policy direction, keep generator yards and major substations out of direct adjacency and require a larger buffer than for the enclosed server building.
- Noise: retain Title 9’s receiving-zone limits, but add data-center methods: pre-project ambient baseline; octave-band and low-frequency analysis; tonal and impulsive penalties; normal, full-cooling, generator-test and credible emergency modes; measurement at the receiving property and inside the nearest sensitive receptor where warranted; post-opening verification.
- Generators: distinguish emergency outage operation from commissioning, testing and demand-response/routine generation. Cap and report non-emergency hours; require synchronized-test analysis rather than one-engine assumptions; locate fuel and exhaust away from sensitive receptors.
- Air and environmental justice: require cumulative analysis of diesel/gas engines, construction, truck trips and nearby industrial sources. Give special attention to communities already bearing high pollution loads. Do not assume “emergency” equipment has no operating impact.
- Water and heat: require annual and peak-day demand, cooling mode, cycles of concentration, blowdown destination, fire flow and drought/emergency plan. Air or closed-loop cooling should receive a preference, not an automatic pass, because energy and heat effects remain.
- Agriculture: avoid fragmenting productive farmland, impairing drains/canals, creating incompatible glare/noise, or using an agricultural zone merely because acreage is cheap.
- Airport, flood, habitat and seismic constraints: map these as exclusions or conditional layers before identifying a preferred site.
- Building and site design: screen mechanical equipment; control lighting at property lines; place noisy plant at the interior; preserve emergency access; require landscape/buffer survival standards suited to desert conditions.
How to handle projects already in process
There is no single “grandfathered” category. County Counsel should create a project-by-project entitlement table.
Questions for each project
- What applications have been submitted, and were they deemed complete?
- What permits, maps, zone changes, specific plans or development agreements were actually approved?
- Was any tentative map expressly a vesting tentative map?
- Has a building permit been issued, and has the developer performed substantial work and incurred substantial liabilities in good-faith reliance on it?
- What precise use, capacity, phase and parcel does any claimed right cover?
- What approvals remain discretionary?
- Which building, fire, health, nuisance and operating requirements remain applicable?
Legal reference points
- California’s traditional vested-right rule is narrow. Avco addresses the conflict between reliance on approvals and later regulation; the common shorthand is a valid building permit plus substantial work and liabilities in reliance, but County Counsel must apply the actual facts.
- A vesting tentative map can confer rights to proceed in substantial compliance with specified ordinances, policies and standards. Gov. Code §66498.1.
- A development agreement can lock in rules governing permitted uses, density, design and construction unless the agreement provides otherwise. Gov. Code §§65864-65866.
- CEQA applies to discretionary approvals including zoning amendments, variances, CUPs and tentative maps unless exempt. Pub. Resources Code §21080.
- An urgency interim ordinance is authorized under Gov. Code §65858 when the required health, safety and welfare findings and procedures are met. Its use, duration and effect on pending matters require County Counsel review.
Transition recommendation
- Apply new rules prospectively to new applications.
- Apply them to pending applications to the extent legally allowed, based on the entitlement table rather than a blanket label.
- Honor a demonstrated vested right only to its documented scope.
- Preserve generally applicable building, fire, health, nuisance and operating authority where the law allows.
- Offer a defined transition process: applicant submits its claimed vesting instruments; County Counsel issues a written scope determination; staff identifies which new standards remain applicable.
- Do not let a lot merger, pre-application discussion, feasibility study or utility inquiry stand in for a land-use entitlement.
Sources
- Imperial County Land Use Element: https://www.icpds.com/assets/planning/land-use-element/land-use-element-2015.pdf
- Title 9 zoning provisions: https://www.icpds.com/assets/5-Zoning-Areas-Established-.pdf
- Title 9 noise: https://www.icpds.com/assets/planning/ordinances/title-9-div-7-2015.pdf
- California CEQA applicability, PRC §21080: https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PRC§ionNum=21080
- Interim zoning, Gov. Code §65858: https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV§ionNum=65858
- Development agreements, Gov. Code §§65864-65866: https://leginfo.legislature.ca.gov/faces/codes_displayText.xhtml?article=2.5.&chapter=4.&division=1.&lawCode=GOV&title=7.
- Vesting tentative maps, Gov. Code §66498.1: https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV§ionNum=66498.1.
- Avco: https://scocal.stanford.edu/opinion/avco-community-developers-inc-v-south-coast-regional-com-27961
- Loudoun County official standards project: https://www.loudoun.gov/datacenterstandards
- Loudoun data-center ordinance: https://online.encodeplus.com/regs/loudouncounty-va-zo/doc-viewer.aspx?secid=859
- Prince William County overlay example: https://princewilliamcounty.elaws.us/code/coor_ch32_artv_pt509_sec32-509.02
- Fairfax County 2024 amendment example: https://www.fairfaxcounty.gov/planning-development/sites/planning-development/files/Assets/Documents/zoning%20ordinance/adopted%20amendments/ZO_112_1-2024-9.pdf
Legal caveat: This is a policy research paper, not a legal opinion. County Counsel should determine the effect of any existing approval or claimed vested right and review all transition language.
Draft Findings and Recommendations Structure
Imperial County Data Center Advisory Committee | Board package outline
Executive finding
Imperial County’s current code allows enclosed data centers in industrial zones but does not scale review to electric demand or address the combined infrastructure and compatibility effects of modern high-load campuses. The County should replace a binary allow/deny debate with a tiered, evidence-based system that identifies what fits, where it fits and what must be proven before approval.
Proposed findings
Finding 1 - The use already exists in Title 9
Title 9 permits an enclosed data center in M-1, permits data centers in M-2, and carries M-2 uses into M-3. A data-center yard requires a CUP in M-1.
Recommendation: retain a path for suitable projects but define the use, campus, yard, accessory generation, utility versus IT load and common-control phases.
Finding 2 - Current review is not proportional to scale
The located code does not distinguish a small server facility from a 20 MW or 300 MW campus.
Recommendation: adopt load tiers: administrative under 5 MW in selected industrial settings; CUP and infrastructure screen at 5-under 20 MW; enhanced CUP and IID record at 20-under 50 MW; specific plan/development agreement at 50 MW+ or for an aggregated campus.
Finding 3 - Twenty MW is a useful planning unit, not available capacity
IID’s 2026 tariff applies at 20 MW or more and an 80% minimum load factor, but no public map proves a 20 MW block is deliverable at a named parcel.
Recommendation: require IID confirmation of point of interconnection, deliverable MW/MWh, upgrade cost, power supply, schedule and curtailment before land-use approval becomes effective.
Finding 4 - Location should follow infrastructure and compatibility
Industrial zoning alone does not establish adequate power, water, fire flow, roads, drainage or separation from sensitive uses.
Recommendation: adopt a suitability overlay/atlas using parcel, zoning, 92/161/230-kV proximity, water-purveyor, flood, airport, habitat, agriculture, housing, school and environmental-justice layers. Treat transmission proximity only as a screen.
Finding 5 - Water claims need a common accounting method
Cooling technology, peak-day demand, annual use, blowdown, fire flow and drought operation can produce very different impacts.
Recommendation: require an independently reviewed water budget, named legal supplier, peak/annual volumes, cooling mode, fire flow, blowdown disposal and enforceable cap. Prefer low-water designs without making technology alone dispositive.
Finding 6 - Backup generation is a land-use issue
Large engine arrays can create noise, exhaust, fuel, fire and cumulative air effects even when called emergency equipment.
Recommendation: distinguish outage operation, testing, commissioning and routine/demand-response generation; require cumulative air/acoustic review, synchronized-test modeling, non-emergency hour caps and logs, and greater separation from sensitive uses.
Finding 7 - Existing noise limits are necessary but incomplete
Title 9 sets receiving-zone dBA limits, but modern data centers raise tonal and low-frequency noise and multiple operating modes.
Recommendation: add baseline, octave-band/low-frequency, tonal/impulsive, full-cooling, generator-test and post-opening verification requirements.
Finding 8 - Public capacity should not be reserved for speculation
The current use listing contains no data-center-specific proof of capital, equipment orders, milestone or expiration standard.
Recommendation: require parcel control, financing evidence, applicant-funded IID obligations, staged load-ramp milestones, automatic expiration and decommissioning security.
Finding 9 - Existing projects require individual legal analysis
“Pending” and “grandfathered” are not legal conclusions. Rights may arise from specific permits, vesting tentative maps, development agreements or common-law vesting, each with a defined scope.
Recommendation: have County Counsel publish a project-by-project entitlement table and written scope determination. Apply new rules prospectively and to pending matters to the extent legally allowed; honor proven rights only to their documented scope.
Finding 10 - The County can offer a constructive development path
A clear list of preferred study areas and evidence requirements can protect communities while reducing wasted applicant and staff effort.
Recommendation: create a pre-application fatal-flaw screen and publish the suitability methodology, application checklist, review sequence and standard conditions.
Implementation package
- General Plan policy amendment on data-center location, infrastructure and compatibility.
- Title 9 definitions, tier table, use permissions and anti-segmentation rule.
- Data Center Suitability Overlay and atlas.
- Enhanced CUP findings and application checklist.
- Model specific-plan/development-agreement terms for system-scale campuses.
- Operating verification and enforcement schedule.
- Transition ordinance and County Counsel entitlement table.
- Annual public report: permitted/operating MW, water use, generator testing, compliance and expired approvals, protecting customer confidentiality.
Remaining evidence before final adoption
- IID anonymized top-load bands, substation-area headroom format, queue, study backlog and resource assumptions.
- Water-purveyor capacity and fire-flow data for candidate areas.
- Air district rules and cumulative burden analysis for generator fleets.
- Fire authority standards for BESS, fuel and emergency access.
- Parcel-level zoning, ownership, airport, flood and habitat layers.
- County Counsel analysis of pending applications and claimed vested rights.
- Fiscal study of jobs, tax revenue, public-service cost and upgrade/security terms by project scale.
- Public testimony recorded by topic and tied to evidence.